Page 27 - Case Study Annual 2018
P. 27

LAA Gold Award







          to a drawbar configuration. The reconfigure        in the mire at the shore edge. The team
          in Harare involved the offloading of the           began the challenging manoeuvres to free
          boat, removing the gooseneck and fitting a         the load and turned the vehicle an incredible
          drawbar and header, together with turning          180° allowing it to start reversing toward the
          the boat 180° on the trailer for the boat to       water. For the first 350m, it seemed as if the
          travel stern first down the escarpment. In         vessel would finally make it into the lake,
          doing so, they were able to shorten the trailer    however, with 150m to go, the surface began
          by 5m and reduce the swing clearance on            to crumble underneath the team, bringing an
          the rear of the load, thus allowing it to sweep    immediate halt to the vessel’s progress.
          past rock faces on the route without having          With the end of the road literally within
          to excavate the cliff walls.                       touching distance, a new plan had to be
            The reconfigure in Harare involved the           made, which involved importing 220 cubic
          transport of equipment from Johannesburg           metres of gravel from a local quarry and
          and temporary import of equipment. An              laying down a temporary surface to the lake
          earthmoving contractor was also employed           shore. The newly constructed roadway held
          to make adjustments to the last 10km of dirt       out for the first 100m, but as the houseboat
          road that would ultimately take the load to        started its turn, the surface once again
          the shore. As the houseboat moved down the         started breaking up. The team resorted to
          escarpment, it became evident that the route       adapting the rigging team’s timber intended
          survey conducted was accurate to within a          for the offloading procedure into a temporary
          few centimetres.                                   wooden road, allowing the load to finally inch
            The vessel arrived at the Lake Harvest           its way to the water.
          harbour and with the African Dream now               So, after three months on the road, the
          in sight of the water, only 500m from the          Manline Mega team delivered the boat on
          shoreline, the expectation was that she would      11 December and the African Dream launched
          glide hassle-free down the final stretch.          on 18 December, much to the delight of its
          However, tight turns and a ground surface          the French owners. This project required skill,
          unable to withstand the weight of the load         tenacity and innovative thinking, which the
          caused the trailer to become bogged down           Manline Mega team delivered wholeheartedly. •










































          The Logistics News Case Study Annual 2018                                                           25
   22   23   24   25   26   27   28   29   30   31   32